    Project Timeline

     
    The construction of the "Reshaping Opportunities for Success 2015-2020" project is expected to take about four years, starting in the spring / summer of 2016 and ending in the summer of 2020. The plan is financed through a 30-year bond.
     

    Construction Timeline

    Construction on the project would begin in the spring / summer of 2016 and the entire project would be completed by the summer of 2020.

    Here is a breakdown of the phases of construction:

    Schematic Design Stage

    June - Nov. 2014: Schematic Design Planning

    Design & Bidding Stages

    • Dec. 2014 - May 2015: High School, Junior High and Phase I of Elementary School Project

    • Oct. 2015 - March 2016: Southwest Renovation Project

    • Oct. 2016 - March 2017: Phase II of Elementary School Project

    Construction Stages

    • June 2015 - Aug. 2017: High School and Junior High School Projects

    • June 2015 - Aug. 2016: Phase I of Elementary School Project

    • June 2016 - Aug. 2017: Phase II of Elementary School Project

    • June 2017 - Aug. 2018: Southwest Renovation Project

    Financing Timeline

    This project will be paid for through a 30-year financing bond. The bond involves two stages, and in order to minimize the impact to voters a portion of the bond would not be issued until after the district's current bond obligation, received in 1998, is fulfilled. Click here to see a chart showing the financial structure of the bond.